The Challenge
Manage a federated model environment across 11 design packages and six contractor packages for a €340M port expansion, with information exchanges governed by a live programme.
The Outcome
All 17 information exchange milestones met on programme. Federated model maintained as a live coordination tool through construction completion.
The
Programme-scale federation
With 11 design packages and 6 contractor packages running concurrently, the information management task exceeded what any single design consultant could manage alongside their own design responsibility. A dedicated information manager was required.
Multi-consultant coordination
Six different design consultants and six contractors were producing models in different software, to different standards, on different programmes. A neutral information manager was needed to set the rules and enforce them consistently.
Construction-driven coordination
Unlike a standard design project, the coordination cycles needed to align with the construction programme rather than design stage gates. This required a fundamentally different approach to information exchange scheduling.
What
What
Programme-driven coordination
Multi-jurisdiction
How
Programme-aligned milestones
We replaced the standard stage-gate information exchange model with 17 programme-aligned milestones, each defined by the construction activity it supported. Model content requirements were specific to each milestone rather than following a generic LOD progression.
48-hour review commitment
Every model submission received a written acceptance or rejection within 48 hours. This was non-negotiable — in a live construction programme, a submission sitting in review for a week creates downstream delays across multiple packages.
Neutral information management
As the information manager, we were independent of all design and contractor packages. This neutrality was essential for enforcement — rejecting a submission from one consultant could not be influenced by a commercial relationship with another.
The
Port infrastructure projects combine the scale and programme complexity of major civil engineering with the multi-discipline coordination challenges of a building project. The Rotterdam expansion included quay wall reconstruction, crane rail installation, utilities rerouting, and a new operations building — each with different design consultants and different coordination requirements.
We were appointed as information manager across the full programme, responsible for the federated coordination environment, information exchange governance, and model quality at each stage gate.
The federated model environment was established across 11 design packages and six contractor packages, with weekly coordination cycles structured around the construction programme rather than a standard design-stage cadence.
Information exchange governance was the critical delivery — a programme of 17 information exchange milestones, each with defined model content, quality criteria, and acceptance procedures. We managed the exchange process, reviewed submissions against the criteria, and issued acceptance or rejection with written feedback within 48 hours.
At construction completion, the federated model reflected the as-built condition across all 17 packages, with a documented evidence trail in the CDE for every information exchange milestone.
What
Federated model environment
A managed federation environment across all 17 packages, with weekly coordination cycles and defined procedures for model submission, review, and acceptance.
Information exchange programme
17 defined milestones with model content requirements, quality criteria, and acceptance procedures specific to each milestone and the construction activity it supported.
Submission review reports
Written acceptance or rejection for every model submission within 48 hours, with specific feedback on non-conformances and required corrections.
CDE administration
Aconex and ProjectWise environments configured for multi-consultant access, with role-based permissions, submission workflows, and automated notifications aligned to the information exchange programme.
As-built federated model
A complete as-built federation reflecting the installed condition across all 17 packages, with a documented evidence trail in the CDE for every information exchange milestone.
Technology
“Seventeen information exchange milestones across a live construction programme, all on time. The information management was what kept the programme together — without it we would have been managing model submissions by email.”
Programme Manager
Client Representative