Federated model management for a port infrastructure expansion in Rotterdam
Back to Case Studies
InfrastructureNov 2024

Federated

Port Authority (via Programme Manager)

€340MProgramme value
17Design and contractor packages federated
17/17Information exchange milestones on programme
48hrsMaximum review turnaround on submissions

The Challenge

Manage a federated model environment across 11 design packages and six contractor packages for a €340M port expansion, with information exchanges governed by a live programme.

The Outcome

All 17 information exchange milestones met on programme. Federated model maintained as a live coordination tool through construction completion.

/Why They Needed Help

The

Programme-scale federation

With 11 design packages and 6 contractor packages running concurrently, the information management task exceeded what any single design consultant could manage alongside their own design responsibility. A dedicated information manager was required.

Multi-consultant coordination

Six different design consultants and six contractors were producing models in different software, to different standards, on different programmes. A neutral information manager was needed to set the rules and enforce them consistently.

Construction-driven coordination

Unlike a standard design project, the coordination cycles needed to align with the construction programme rather than design stage gates. This required a fundamentally different approach to information exchange scheduling.

/Scope of Work

What

01Federated model environment setup and management
02Information exchange governance across 17 packages
03Model submission review and 48-hour acceptance/rejection
04Construction programme-aligned coordination cycles
05CDE administration and access management
06As-built federated model at construction completion
/Key Challenges

What

Programme-driven coordination

Multi-jurisdiction

/Our Strategy

How

01

Programme-aligned milestones

We replaced the standard stage-gate information exchange model with 17 programme-aligned milestones, each defined by the construction activity it supported. Model content requirements were specific to each milestone rather than following a generic LOD progression.

02

48-hour review commitment

Every model submission received a written acceptance or rejection within 48 hours. This was non-negotiable — in a live construction programme, a submission sitting in review for a week creates downstream delays across multiple packages.

03

Neutral information management

As the information manager, we were independent of all design and contractor packages. This neutrality was essential for enforcement — rejecting a submission from one consultant could not be influenced by a commercial relationship with another.

/Full Story

The

Port infrastructure projects combine the scale and programme complexity of major civil engineering with the multi-discipline coordination challenges of a building project. The Rotterdam expansion included quay wall reconstruction, crane rail installation, utilities rerouting, and a new operations building — each with different design consultants and different coordination requirements.

We were appointed as information manager across the full programme, responsible for the federated coordination environment, information exchange governance, and model quality at each stage gate.

The federated model environment was established across 11 design packages and six contractor packages, with weekly coordination cycles structured around the construction programme rather than a standard design-stage cadence.

Information exchange governance was the critical delivery — a programme of 17 information exchange milestones, each with defined model content, quality criteria, and acceptance procedures. We managed the exchange process, reviewed submissions against the criteria, and issued acceptance or rejection with written feedback within 48 hours.

At construction completion, the federated model reflected the as-built condition across all 17 packages, with a documented evidence trail in the CDE for every information exchange milestone.

/Deliverables

What

Federated model environment

A managed federation environment across all 17 packages, with weekly coordination cycles and defined procedures for model submission, review, and acceptance.

Information exchange programme

17 defined milestones with model content requirements, quality criteria, and acceptance procedures specific to each milestone and the construction activity it supported.

Submission review reports

Written acceptance or rejection for every model submission within 48 hours, with specific feedback on non-conformances and required corrections.

CDE administration

Aconex and ProjectWise environments configured for multi-consultant access, with role-based permissions, submission workflows, and automated notifications aligned to the information exchange programme.

As-built federated model

A complete as-built federation reflecting the installed condition across all 17 packages, with a documented evidence trail in the CDE for every information exchange milestone.

/Tools Used

Technology

Aconex
Autodesk Navisworks
Bentley ProjectWise
Solibri Model Checker
“Seventeen information exchange milestones across a live construction programme, all on time. The information management was what kept the programme together — without it we would have been managing model submissions by email.”

Programme Manager

Client Representative

/Certifications

Certifications

Our certified management systems support consistent quality, information management and controlled project delivery across the work we do.

Information Management certification

Information Management

Quality Management certification

Quality Management

Information Security certification

Information Security

Environmental certification

Environmental

PLAN · COORDINATE · DELIVER · OPTIMISE ·PLAN · COORDINATE · DELIVER · OPTIMISE ·PLAN · COORDINATE · DELIVER · OPTIMISE ·PLAN · COORDINATE · DELIVER · OPTIMISE ·PLAN · COORDINATE · DELIVER · OPTIMISE ·PLAN · COORDINATE · DELIVER · OPTIMISE ·

Let's

Whether you need BIM coordination, digital engineering or end-to-end project delivery support, our team is ready to help you deliver projects with greater certainty, fewer surprises and stronger collaboration.

Start Your Project