Data Centre
01
Mission-Critical Infrastructure

Data

Federated BIM at LOD 400 for a tier-three hyperscale data centre in the Dubai Investment Park.

/Overview
Data Centre
SCAN 0%
ClientData Centre Operator
LocationDubai, UAE
Year2024
Area28,000 m²
LODLOD 400
DisciplinesMechanical, Electrical, Plumbing, Fire Suppression, Structured Cabling

Data

A 28,000 m² mission-critical facility designed to meet Tier III uptime standards. Our scope covered full MEP coordination across five disciplines — power, cooling, fire suppression, structured cabling, and security systems — delivered as a single federated Revit model at LOD 400. Clash detection cycles were run weekly against the structural and architectural models, resolving over 2,400 issues before construction commenced.

BIM ModelingMEP Coordination
/Why They Needed Help

Where

01

No Single Source of Truth

Five MEP disciplines were being modelled by separate subcontractors with no federated environment.

02

Uptime Left No Room for Error

Tier III redundancy requirements meant a single unresolved clash could compromise N+1 resilience once construction began.

03

RFI Volume Eating the Programme

Early coordination gaps were generating enough RFIs to threaten the construction schedule.

04

No In-House Coordination Capacity

The operator's own team had the operational expertise but not the modelling bandwidth to run federated coordination in-house.

/Project Gallery

A look inside the project.

/Scope of Work

Where

BIM ModelingMEP Coordination
01
Federated MEP Modelling (LOD 400)
02
Multi-Discipline Clash Detection
03
BIM Execution Plan Authoring
04
Construction-Issue Coordination
/Key Project Challenges

What

CH.01

Five Disciplines, One Model

Power, cooling, fire suppression, structured cabling, and security all had to resolve inside a single federated model.

CH.02

Tier III Uptime Tolerance

Redundant systems left almost no spatial slack — every reroute had to preserve N+1 resilience paths across the entire facility.

CH.03

Weekly Clash Cadence Under Pressure

Running clash cycles weekly against a live structural model meant issues had to be triaged and closed before the next design freeze.

CH.04

RFI Reduction Target

Contractors needed a model clean enough to build from directly, since the project's RFI budget assumed a 60% reduction against the portfolio average.

/Execution Strategy

How

Federate & Baseline

All five MEP disciplines were brought into a single federated Revit environment against the architectural and structural baseline.

01
02

Coordinate Weekly

Structured clash-detection cycles ran every week, with BCF issues assigned directly to discipline leads.

Resolve at Source

Over 2,400 clashes were closed by adjusting routing at the modelling stage.

03
04

Hand Off Construction-Ready

Discipline-specific issue sheets were issued directly to site, coordinated against the structural model.

/Solution Delivered

What

Layer 01

Federated MEP Model

LOD 400 model covering all five MEP disciplines, authored to the project BEP.

Layer 02

Clash Detection Reports

Weekly BCF-based clash reports with issue ownership assigned to discipline leads. Over 2,400 clashes resolved.

Layer 03

BIM Execution Plan

Project-specific BEP written to ISO 19650-2.

Layer 04

Construction Issue Sheets

Discipline-specific issue sheets coordinated with the structural model.

/Business Impact

What

0RFI reduction vs portfolio average
0Clashes resolved pre-construction
0Disciplines federated into one model
0Tier III N+1 compliance maintained
/Tools Used

What

R
Autodesk RevitBIM Authoring
N
Navisworks ManageModel Coordination
B
BIM 360Cloud Collaboration
B
BIMcollab BCFIssue Tracking
/Client Testimonial

“Neutec's coordination model became the one document every contractor trusted on site.”

Facilities Director

Data Centre Operator

/FAQ

Questions

/Certifications

Certifications

Our certified management systems support consistent quality, information management and controlled project delivery across the work we do.

Information Management certification

Information Management

Quality Management certification

Quality Management

Information Security certification

Information Security

Environmental certification

Environmental

PLAN · COORDINATE · DELIVER · OPTIMISE ·PLAN · COORDINATE · DELIVER · OPTIMISE ·PLAN · COORDINATE · DELIVER · OPTIMISE ·PLAN · COORDINATE · DELIVER · OPTIMISE ·PLAN · COORDINATE · DELIVER · OPTIMISE ·PLAN · COORDINATE · DELIVER · OPTIMISE ·

Let's

Whether you need BIM coordination, digital engineering or end-to-end project delivery support, our team is ready to help you deliver projects with greater certainty, fewer surprises and stronger collaboration.

Start Your Project