Federated BIM at LOD 400 for a tier-three hyperscale data centre in the Dubai Investment Park.

Data
A 28,000 m² mission-critical facility designed to meet Tier III uptime standards. Our scope covered full MEP coordination across five disciplines — power, cooling, fire suppression, structured cabling, and security systems — delivered as a single federated Revit model at LOD 400. Clash detection cycles were run weekly against the structural and architectural models, resolving over 2,400 issues before construction commenced.
Where
No Single Source of Truth
Five MEP disciplines were being modelled by separate subcontractors with no federated environment.
Uptime Left No Room for Error
Tier III redundancy requirements meant a single unresolved clash could compromise N+1 resilience once construction began.
RFI Volume Eating the Programme
Early coordination gaps were generating enough RFIs to threaten the construction schedule.
No In-House Coordination Capacity
The operator's own team had the operational expertise but not the modelling bandwidth to run federated coordination in-house.
A look inside the project.












Where
What
Five Disciplines, One Model
Power, cooling, fire suppression, structured cabling, and security all had to resolve inside a single federated model.
Tier III Uptime Tolerance
Redundant systems left almost no spatial slack — every reroute had to preserve N+1 resilience paths across the entire facility.
Weekly Clash Cadence Under Pressure
Running clash cycles weekly against a live structural model meant issues had to be triaged and closed before the next design freeze.
RFI Reduction Target
Contractors needed a model clean enough to build from directly, since the project's RFI budget assumed a 60% reduction against the portfolio average.
How
Federate & Baseline
All five MEP disciplines were brought into a single federated Revit environment against the architectural and structural baseline.
Coordinate Weekly
Structured clash-detection cycles ran every week, with BCF issues assigned directly to discipline leads.
Resolve at Source
Over 2,400 clashes were closed by adjusting routing at the modelling stage.
Hand Off Construction-Ready
Discipline-specific issue sheets were issued directly to site, coordinated against the structural model.
What
Federated MEP Model
LOD 400 model covering all five MEP disciplines, authored to the project BEP.
Clash Detection Reports
Weekly BCF-based clash reports with issue ownership assigned to discipline leads. Over 2,400 clashes resolved.
BIM Execution Plan
Project-specific BEP written to ISO 19650-2.
Construction Issue Sheets
Discipline-specific issue sheets coordinated with the structural model.
What
What
“Neutec's coordination model became the one document every contractor trusted on site.”
Facilities Director
Data Centre Operator
Questions
Other
Audited
Every engagement is delivered against certified management systems — not just claimed adherence.

Information Management
BIM delivery

Quality Management
Process & delivery

Information Security
Data handling

Environmental
Sustainability