Corporate
Integrated MEP design and BIM coordination for a 14,000 m² corporate headquarters in BKC.
Corporate
A financial services firm relocating its India headquarters required a fully coordinated MEP design package delivered to an accelerated programme. We took the project from concept MEP through to construction documentation in 18 weeks, working in parallel with the architect and structural engineer on a shared Revit environment.
BIM coordination was run continuously throughout the design phase rather than as a separate clash-detection exercise at the end — allowing issues to be resolved as they arose rather than accumulated. The result was a construction-issue model with fewer than 40 residual clashes across the entire building.
Where
Relocation Deadline Wasn't Moving
The firm's India HQ relocation date was fixed, leaving an 18-week window for MEP design that would normally take longer.
Designs Were Still in Motion
Architecture and structure were both evolving in parallel, so MEP had to be coordinated against a moving target, not a frozen baseline.
Clash Clean-Up Always Came Too Late
Previous projects had left coordination to a single end-stage exercise, by which point fixes were expensive and slow.
No Margin for Rework
With the programme this tight, every clash caught late was a clash the schedule couldn't absorb.
Where
What
18-Week Accelerated Programme
The full MEP design had to move from concept through construction documentation on a compressed timeline set by the relocation deadline.
Parallel Design Development
MEP had to progress in a shared Revit environment alongside the architect and structural engineer as their designs were still moving.
Continuous Rather Than End-Stage Coordination
Running clash detection throughout the design, instead of as a final exercise, meant surfacing issues earlier — while there was still time to act on them.
Residual Clash Target
The construction-issue model had to land under 40 residual clashes across the whole building, a tight bar for an 18-week programme.
How
Move Fast from Concept
An outline mechanical and electrical strategy was agreed early, covering system selection and spatial requirements before detailed design began.
Share One Environment
MEP, architecture, and structure worked inside a shared Revit environment rather than exchanging files on a stage-gated schedule.
Coordinate Continuously
Weekly coordination reviews resolved clashes as they appeared, rather than accumulating them for a single late-stage clean-up.
Issue Clean Construction Documents
The final MEP drawing package and NBS specifications were issued for tender with fewer than 40 residual clashes.
What
Concept MEP Report
Outline mechanical and electrical strategy report covering system selection, load estimates, and spatial requirements.
Construction-Issue Drawings
Full MEP drawing package issued for tender and construction, coordinated and clash-free.
BIM Coordination Model
Federated LOD 350 model maintained throughout the design phase with weekly coordination reviews.
Specifications Package
NBS-format mechanical and electrical specifications aligned to the construction drawings.
What
What
“Eighteen weeks from concept to construction issue is an aggressive ask. Neutec kept the coordination tight enough that we never lost time to clashes we should have caught earlier.”
Head of Real Estate
Financial Services Firm
Proof
Data Centre Operator
Dubai, UAE · 2024
Data Centre
60%
RFI reduction vs portfolio average
2,400+
Clashes resolved pre-construction
5
Disciplines federated into one model
Federated BIM at LOD 400 for a tier-three hyperscale data centre in the Dubai Investment Park.
Manufacturing Firm
Pune, India · 2024
Industrial Facility
100%
Site captured in a single 3-day mobilisation
<1cm
Point cloud registration accuracy
0
Return site visits required
Point-cloud capture and as-built modelling for a 45,000 m² brownfield manufacturing plant.
Commercial Developer
London, UK · 2023
Commercial Tower
5
Project stages carried through one federated model
100%
COBie asset data delivered at handover
Live
BMS integration achieved from as-built model
Virtual design and construction programme for a 22-storey City of London office development.
Mixed-Use Developer
Singapore · 2023
Mixed-Use Development
18%
Cooling load reduction vs baseline
6
Atrium massing options simulated
LOD 350
Coordinated MEP model delivered clash-free
Computational fluid dynamics analysis and full MEP design for a mixed-use podium block in Marina Bay.
Real Estate Investment Group
Doha, Qatar · 2022
Mixed-Use Complex
5
Extension massing options evaluated
0
Tenant disruption during capture
Lawson
Criteria compliance achieved at podium level
Post-occupancy scan programme and wind comfort analysis for an existing mixed-use complex in West Bay.
Airport Authority
Riyadh, Saudi Arabia · 2024
Airport Terminal
3,800+
Clashes resolved pre-construction
7
MEP disciplines federated
62,000 m²
Terminal area coordinated
Full MEP coordination and BIM management for a new international terminal expansion at King Khalid Airport.
Healthcare Trust
Toronto, Canada · 2023
Hospital Complex
<60
Residual clashes at construction issue
7
Floors coordinated in one federated model
100%
HTM 03-01 HVAC compliance
Full MEP design and BIM coordination for a 320-bed acute care hospital expansion in downtown Toronto.
Residential Developer
Abu Dhabi, UAE · 2024
Residential Towers
51,000 m²
Twin-tower area coordinated
LOD 400
Delivered across both towers
0
Cross-tower coordination conflicts at issue
Federated architectural and MEP modelling for a twin-tower residential development on Abu Dhabi's Corniche.
Logistics Operator
Singapore · 2022
Logistics Hub
72,000 m²
Facility captured in one mobilisation
<1cm
Registration accuracy across the full site
0
Additional site visits required for phase 1 design
Reality capture and as-built modelling for a 72,000 m² logistics and distribution hub at Jurong.
University Estates
Manchester, UK · 2023
University Campus
100%
FM system import success at handover
LOD 500
As-built model delivered and verified
0
Manual asset entries required post-handover
BIM management and digital twin delivery for a new STEM faculty building on a live university campus.
Hospitality Group
Dubai, UAE · 2022
Hotel Tower
<30
Residual clashes at construction issue
420
Rooms coordinated to LOD 400
9 mo
Concept to construction issue
Integrated MEP design and BIM coordination for a 420-key luxury hotel tower in Dubai Marina.
Technology Firm
Bangalore, India · 2023
Tech Campus
38,000 m²
Campus gross area
LOD 350
Model fidelity
3
Buildings coordinated
Full MEP design and BIM coordination for a three-building technology campus in the Electronic City corridor.
Sports Authority
Cape Town, South Africa · 2023
Stadium
3,100+
Clashes resolved pre-construction
42,000
Seat capacity
LOD 400
Model fidelity
MEP coordination and clash detection for a 42,000-seat multi-purpose stadium in the Cape Winelands.